CASE STUDY
How Chamco Helped A Decommissioned Mine Meet and Maintain its Environmental Obligations
Project Background
In 2019, a decommissioned mine in British Columbia needed to update its existing barge to meet strict environmental requirements. The barge had reached the end of its lifespan and was also getting damaged from being dragged in and out of the pond.
The customer was keen to keep the barge, and turned to Chamco to understand the different options available that were cost-effective and would allow the mine to comply with its environmental responsibilities.
The Challenge
Although the mine was no longer operational, the mine owner was still responsible for water reclamation and meeting strict environmental obligations. To meet their environmental obligations, the mine needed to ensure water levels are kept low, and the mine pit needed to be dewatered regularly so the water could be treated and returned to the environment.
The mine’s existing barge had four pumps that had been performing water reclamation. Every spring, the barge had to be dragged over a rough surface and placed in the pond. The four pumps then had to be assembled and installed on the barge, as they extended below the barge depth in order to reach the water with the reduced minerals.
The barge was aging and suffering from wear and tear from being constantly moved. It was also a challenge to move the barge back and forth and have to keep pulling the pumps out before they could bring it back to shore.
Why the Mine Chose Chamco
Because Chamco had originally installed the barge and there was an existing positive relationship, Chamco was the obvious choice to support the mine once the barge had reached the end of its lifecycle. The mine knew and trusted our experts and appreciated the fact that they presented numerous options to help them make an informed decision.
The Solution
Chamco worked closely with the customer to provide various options to upgrade the barge. One option was to retrofit and fix the barge in the water and fit a de-icing system, leaving the barge in the pond year-round. Another option, which Chamco believed was the best choice, was to replace the barge with a shore-based system.
Ultimately, the customer chose the shore-based option, as it offered a cost-effective solution that would require a lot less effort on their part.
The Results
Chamco took the time to work closely with the customer to understand their needs and concerns and provide a custom solution to meet their unique requirements.
Chamco provided a reliable and cost-effective solution to the mine’s challenges which allowed them to pump water from deep down, treat it, and repurpose it with ease. This helped them consistently meet and maintain their environmental obligations.
“Chamco listened to the customer’s concerns and issues and worked with them to develop a custom product that would meet their requirements now and into the future.”
Other Case Studies
How Chamco Helped a Major Oil and Gas Company Standardize Air Packages Across Multiple Locations
chamco2024-07-31T14:25:58-06:00In 2013, one of Canada’s largest crude oil and natural gas producers faced challenges with consistency in its air compressor systems across its oil pad fields. The company needed to develop a standardized air compressor package to streamline operations, reduce engineering time, and reduce spare parts inventory across multiple locations.
How Chamco Developed an Innovative Dual-Purpose Fire and Process Pump Package for a BC Mine
chamco2024-04-17T11:40:20-06:00In 2023, a new gold mine in BC needed a fire pump and process water pump package for its process plant that was being constructed. The project presented a unique challenge as the mine wanted to integrate fire suppression and process water functionalities into a single compact system with the wash-down pumps housed in the same building as the fire pump package.
How Chamco Helped A Decommissioned Mine Meet and Maintain its Environmental Obligations
chamco2023-03-31T19:08:48-06:00In 2019, a decommissioned mine in British Columbia needed to update its existing barge to meet strict environmental requirements. The barge had reached the end of its lifespan and was also getting damaged from being dragged in and out of the pond.