CASE STUDY
How Chamco Delivered Reliable Air Compressor Packages for Natural Gas Plant Expansions in Under 12 Weeks
Project Background
In 2020, one of Canada’s largest natural gas resource owners was expanding plants in the Fort Saint John and Grande Prairie areas. They were looking for a turnkey air compressor system that would be able to withstand -45°C temperatures for 4-5 months of the year.
Chamco was awarded the first air compressor package on June 1, 2020, and a second package on December 8, 2020, with the third and fourth packages currently under review.
The Challenge: Short Timelines, Competitor Dishonesty, and Supply Chain Issues
Chamco was responsible for two modular air compressor packages including design and build. The project presented 3 key challenges: short timelines, dishonest competitors, and supply chain issues including a late compressor delivery.
Why This Natural Gas Resource Owner Chose Chamco
Chamco was the only bidder to be able to provide a 10-12 week delivery for the completed package and has maintained that delivery timeframe for all the compressor packages.
Chamco was also upfront with the client from the start about how they came to their compressor sizing selection. Chamco has an engineering proposals team, not just inside salespeople. Their engineers actually look at RFQs and come up with the equipment selection based on best practices.
The Solution
Chamco successfully overcame all of the challenges above to deliver the air compressor packages on time for this client.
The Results
Since being installed at the client’s sites, Chamco’s air compressor packages have been trouble-free with zero downtime and serve the exact purpose for which they were designed. The client has since shared that it was easy to work with Chamco and that Chamco gave them peace of mind by providing them with reliable solutions that met their delivery requirements.
Learn more about how Chamco can help with your project.
Other Case Studies
How Chamco Helped a Major Oil and Gas Company Standardize Air Packages Across Multiple Locations
chamco2024-07-31T14:25:58-06:00In 2013, one of Canada’s largest crude oil and natural gas producers faced challenges with consistency in its air compressor systems across its oil pad fields. The company needed to develop a standardized air compressor package to streamline operations, reduce engineering time, and reduce spare parts inventory across multiple locations.
How Chamco Developed an Innovative Dual-Purpose Fire and Process Pump Package for a BC Mine
chamco2024-04-17T11:40:20-06:00In 2023, a new gold mine in BC needed a fire pump and process water pump package for its process plant that was being constructed. The project presented a unique challenge as the mine wanted to integrate fire suppression and process water functionalities into a single compact system with the wash-down pumps housed in the same building as the fire pump package.
How Chamco Helped A Decommissioned Mine Meet and Maintain its Environmental Obligations
chamco2023-03-31T19:08:48-06:00In 2019, a decommissioned mine in British Columbia needed to update its existing barge to meet strict environmental requirements. The barge had reached the end of its lifespan and was also getting damaged from being dragged in and out of the pond.