CASE STUDY
How Chamco Helped a General Contractor Design and Install a Floating Pump System For a Municipal Customer
Project Background
In 2021, a municipality in the USA hired a general contractor to install a floating pump system to feed the new water intake for a water treatment plant.
To support this project, the general contractor partnered with Chamco to design an open deck-style floating pump system suitable for installation on a recreational pond.
The Challenge
Chamco faced several unique challenges due to the location of this project.
Why the Customer Chose Chamco
Chamco was competing against another company for the project bid, but the municipality and general contractor ultimately decided to move forward with Chamco’s design because they recognized that Chamco had the expertise and experience to successfully complete the project.
Unlike the competitor’s design, which included barrels to float the pumps, Chamco’s design included a steel hull with a centre wet well to protect the pumps. The wet well was designed with inlet screens, ensuring the water entering the wet well did not contain debris. Additionally, Chamco attached agitators to the screen area to keep the water moving, deterring small fish from entering.
Because the floating pump system was to be installed away from shore, Chamco’s design featured a cantilever crane that could extend over the water. With this design, the customers’ service boat could position itself under the cantilever crane for the removal of the pumps or motors for any maintenance required. Chamco’s naval architect helped ensure that when this heavy equipment was hanging over the edge of the floating pump system, it would remain stable despite the change to its centre of gravity.
Although Chamco’s initial project costs were higher than the competitor’s bid, the open deck-style floating pump system would lead to lower operational costs and fewer potential disruptions down the road. The stable design eliminates the costs of repairing and replacing sunken parts, and the convenience of accessing and mobilizing the pumps and motors reduces labour costs, leading to future savings. Additionally, Chamco’s design allows the floating pump system to adapt seamlessly to changes in the water level.
The Solution
Chamco’s design met all of the unique requirements, ensuring an ongoing flow of new water intake for the municipality’s water treatment plant.
The Results
While the general contractor was responsible for installing the floating pump system, Chamco was present to consult during the installation.
The final installation was completed in April 2023, and the municipality now benefits from a low-maintenance water intake system that doesn’t interfere with recreational activities or harm local wildlife.
“With all the unique aspects of creating this floating pump system, I would say it was a tremendous success.”
Other Case Studies
How Chamco Helped a Major Oil and Gas Company Standardize Air Packages Across Multiple Locations
chamco2024-07-31T14:25:58-06:00In 2013, one of Canada’s largest crude oil and natural gas producers faced challenges with consistency in its air compressor systems across its oil pad fields. The company needed to develop a standardized air compressor package to streamline operations, reduce engineering time, and reduce spare parts inventory across multiple locations.
How Chamco Developed an Innovative Dual-Purpose Fire and Process Pump Package for a BC Mine
chamco2024-04-17T11:40:20-06:00In 2023, a new gold mine in BC needed a fire pump and process water pump package for its process plant that was being constructed. The project presented a unique challenge as the mine wanted to integrate fire suppression and process water functionalities into a single compact system with the wash-down pumps housed in the same building as the fire pump package.
How Chamco Helped A Decommissioned Mine Meet and Maintain its Environmental Obligations
chamco2023-03-31T19:08:48-06:00In 2019, a decommissioned mine in British Columbia needed to update its existing barge to meet strict environmental requirements. The barge had reached the end of its lifespan and was also getting damaged from being dragged in and out of the pond.