CASE STUDY
How Chamco Built the “Cadillac” of Fire Pump Packages for a B.C. Natural Gas Facility

Project Background
A large liquefied natural gas facility under development on the coast of B.C. needed a fire pump package, and the scope was clear: 10,000 GPM of fire suppression capacity, built to operate in a remote coastal environment with zero tolerance for risk.
The Challenge
As Chamco’s largest fire package build to date, this project posed significant challenges.
Why The Customer Chose Chamco
Fire pump packages are subject to stringent standards, and getting them right from the start requires experience. During the proposal phase, Chamco worked closely with the engineering team to align the specifications to NFPA fire pump standards, walking through the differences in detail. That technical dialogue and documentation were extensive, given that the client put a significantly larger team on the file than Chamco typically works with during proposals.
By the time the purchase order was issued, it was clear that Chamco had the deepest knowledge of fire pump standards among the bidders. Chamco had identified the specification problems early, answered the technical questions in detail, and never left a question unresolved.
The Solution

The Results

The fire pump package was delivered on schedule and within budget, and the customer reported full satisfaction with both the product and the process.
This fire pump package stands as one of the most technically demanding projects Chamco has completed, from the scale of the fire demand to the complexity of the specifications and the logistics of getting a fully assembled package to a remote coastal site. It serves as a direct example of Chamco’s ability to work with very difficult specifications and customer demands, and to deliver a successful product.

For the customer, the outcome was a fire protection system built to their exact specification, fully assembled before it left the shop, and ready to connect on arrival at one of the most remote industrial sites in British Columbia.

“They bought every Cadillac item you could buy in a firewater package. They did not spare anything. I’m sure 50 years from now, that firewater package will still be operating.”
Other Case Studies
How Chamco Built the “Cadillac” of Fire Pump Packages for a B.C. Natural Gas Facility
chamco2026-06-17T13:37:31-06:00A liquefied natural gas facility on the B.C. coast became Chamco’s largest and most complicated fire pump package to date. The site required 10,000 GPM of suppression capacity, strict human factor engineering standards, and zero tolerance for risk.
How Chamco Successfully Relocated a Barge at a Remote Mongolia Mine
chamco2025-11-06T08:55:43-07:00In 2023, a major mining company needed to relocate a Chamco-built floating pump house from one tailings pond to a newly constructed second pond. The customer required the barge to be moved fully intact on a strict timeline.
How Chamco Delivered a Functional Showcase Air Compressor System for a Technical Training Facility
chamco2025-10-28T11:21:38-06:00In 2025, a technical training facility in Alberta expanded its workshop and required a new air compressor system. Chamco was tasked with supplying, installing, and piping the system on a tight one-week schedule while meeting strict building specifications.